What is CE?
 Residental Solutions
 Industrial Solutions
 Ask For Quotation
references


TOFAŞ

TOFAŞ, one of the pioneers of the Turkish Automotive Industry, chose to continue operating in partnership with ERENSAN, selecting a steam boiler and hot water boiler for its TOFAŞ TÜRK OTOMOBİL A.Ş. Power Plant renewal project. The company will use an SHW-T 1201100 Hot Water Boiler (8 Bar) and an ESB 500 Steam Boiler.




AĞAOĞLU MY WORLD EUROPE

Ağaoğlu My World Europe Ayazma, one of Istanbul’s symbolic projects, will use the Erensan Cascade System. The project, to be built on 200 decares of land next to the Olympic Stadium in Ayazma-Başakşehir, İstanbul, will be comprised of a total of 3080 residences in 17 blocks and 20 twin villas. In the mechanical installation stage of the project, nine Euromax C 4000 Three-Pass Hot Water Boilers with Integrated Condensing Economizers will be used.

The cascade system will be controlled by an Erensan Euromatic Cascade Control Panel.


İSTWEST

IstWest, one of the most stylish residential projects in İstanbul, will also use the ERENSAN Cascade System. The project to be built on land adjacent to Atatürk Airport in Yenibosna will be comprised of house and residential options ranging from 43 m2 to 210 m2 in a total of 11 blocks. In the mechanical installation stage of the project 3 TR CGas Fueled Three-Pass Condensing Hot Water Boiler units, 1 TR Three-Pass Hot Water Boiler unit, 1 ECOMAX F Condensing Economizer unit and 4 EUROMAX Three-Pass Hot Water Boilers will be used.

The cascade system will be controlled by an Erensan Euromatic Cascade Control Panel.


ERENSAN SECURES ITS LEADERSHIP POSITION WITH THE WASTE HEAT COMBINED CYCLE SOLUTIONS FOR ELECTRICITY GENERATION PLANTS!

Samsun’s YEŞİLYURT ENERJİ ELEKTRİK ÜRETİM A.Ş. will generate the electricity required for its steel factory using Wärtsilä 50SG engines fueled by natural gas. The total engine power will be 145 MW. However, after the completion of the combined cycle Waste Heat Boiler designed by ERENSAN, with the addition of a steam turbine the capacity of the plant will increase to 160 MW at full load.

This plant has been designed by ERENSAN using combined cycle-supporting boilers that enable fast start-up, quick shut-down and high load efficiencies.

ERENSAN’s role in this project is its engineering system design that with proven technologies fulfills the project’s requirements.

ERENSAN will continue to be involved in Combined Cycle Power Plant projects worldwide as the solution partner of industry investors, through its system design, its production and supervision services, and its service support.




  Home | About Us | Products | Service | References | Certificates | Contact | Site Map All rights reserved by erensan° 2007